Notes
Outline
Chapter 3:
Project Integration Management
The Key to Overall Project Success: Good Project Integration Management
Project managers must coordinate all of the other knowledge areas throughout a project’s life cycle
Many new project managers have trouble looking at the “big picture” and want to focus on too many details (See opening case for a real example)
Project integration management is not the same thing as software integration
Project Integration Management Processes
Project Plan Development: taking the results of other planning processes and putting them into a consistent, coherent document—the project plan
Project Plan Execution: carrying out the project plan
Integrated Change Control: coordinating changes across the entire project
Figure 3-1.  Project Integration Management Overview
Figure 3-2. Framework for Project Integration Management
Project Plan Development
A project plan is a document used to coordinate all project planning documents
Its main purpose is to guide project execution
Project plans assist the project manager in leading the project team and assessing project status
Project performance should be measured against a baseline project plan
Attributes of Project Plans
Just as projects are unique, so are project plans
Plans should be dynamic
Plans should be flexible
Plans should be updated as changes occur
Plans should first and foremost guide project execution
Common Elements of a Project Plan
Introduction or overview of the project
Description of how the project is organized
Management and technical processes used on the project
Work to be done, schedule, and budget information
Table 3-1. Sample Outline for a Software Project Management Plan (SPMP)
Stakeholder Analysis
A stakeholder analysis documents important (often sensitive) information about stakeholders such as
stakeholders’ names and organizations
roles on the project
unique facts about stakeholders
level of influence and interest in the project
suggestions for managing relationships
Table 3-2. Sample Stakeholder Analysis
Project Plan Execution
Project plan execution involves managing and performing the work described in the project plan
The majority of time and money is usually spent on execution
The application area or the project directly affects project execution because the products of the project are produced during execution
What Went Wrong?
Many people have a poor view of plans based on past experiences.  Senior managers often require a plan, but then no one follows up on whether the plan was followed.
For example, one project manager said he would meet with each project team leader within two months to review their plans.  The project manager created a detailed schedule for these reviews.  He cancelled the first meeting due to another business commitment.  He rescheduled the next meeting for unexplained personal reasons.  Two months later, the project manager had still not met with over half of the project team leaders.
Why should project members feel obligated to follow their own plans when the project manager obviously did not follow his?
Important Skills for Project Execution
General management skills like leadership, communication, and political skills
Product skills and knowledge (see example of “What Went Right?”)
Use of specialized tools and techniques
Tools and Techniques for Project Execution
Work Authorization System: a method for ensuring that qualified people do work at the right time and in the proper sequence
Status Review Meetings: regularly scheduled meetings used to exchange project information
Project Management Software: special software to assist in managing projects
Integrated Change Control
Integrated change control involves identifying, evaluating, and managing changes throughout the project life cycle (Note:  1996 PMBOK called this process “overall change control”)
Three main objectives of change control:
Influence the factors that create changes to ensure they are beneficial
Determine that a change has occurred
Manage actual changes when and as they occur
Figure 3-3. Integrated Change Control Process
Change Control on Information Technology Projects
Former view: The project team should strive to do exactly what was planned on time and within budget
Problem: Stakeholders rarely agreed up-front on the project scope, and time and cost estimates were inaccurate
Modern view: Project management is a process of constant communication and negotiation
Solution:  Changes are often beneficial, and the project team should plan for them
Change Control System
A formal, documented process that describes when and how official project documents and work may be changed
Describes who is authorized to make changes and how to make them
Often includes a change control board (CCB), configuration management, and a process for communicating changes
Change Control Boards (CCBs)
A formal group of people responsible for approving or rejecting changes on a project
Provides guidelines for preparing change requests, evaluates them, and manages the implementation of approved changes
Includes stakeholders from the entire organization
Making Timely Changes
Some CCBs only meet occasionally, so it may take too long for changes to occur
Some organizations have policies in place for time-sensitive changes
“48 hour policy” allowed project team members to make decisions, then they had 48 hours reverse the decision pending senior management approval
Delegate changes to the lowest level possible, but keep everyone informed of changes
Configuration Management
Ensures that the products and their descriptions are correct and complete
Concentrates on the management of technology by identifying and controlling the functional and physical design characteristics of products
Configuration management specialists identify and document configuration requirements, control changes, record and report changes, and audit the products to verify conformance to requirements
Table 3-3. Suggestions for Managing Integrated Change Control
View project management as a process of constant communications and negotiations
Plan for change
Establish a formal change control system, including a Change Control Board (CCB)
Use good configuration management
Define procedures for making timely decisions on smaller changes
Use written and oral performance reports to help identify and manage change
Use project management and other software to help manage and communicate changes