Notes
Outline
Chapter 5:
Project Time Management
Importance of Project Schedules
Managers often cite delivering projects on time as one of their biggest challenges
Average time overrun from 1995 CHAOS report was 222%; improved to 63% in 2001 study
Time has the least amount of flexibility; it passes no matter what
Schedule issues are the main reason for conflicts on projects, especially during the second half of projects
Figure 5-1. Conflict Intensity Over the Life of a Project
Project Time Management Processes
Project time management involves the processes required to ensure timely completion of a project.  Processes include:
Activity definition
Activity sequencing
Activity duration estimating
Schedule development
Schedule control
Where Do Schedules Come From? Defining Activities
Project schedules grow out of the basic document that initiate a project
Project charter includes start and end dates and budget information
Scope statement and WBS help define what will be done
Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done
Activity Sequencing
Involves reviewing activities and determining dependencies
Mandatory dependencies: inherent in the nature of the work; hard logic
Discretionary dependencies: defined by the project team; soft logic
External dependencies: involve relationships between project and non-project activities
You must determine dependencies in order to use critical path analysis
Project Network Diagrams
Project network diagrams are the preferred technique for showing activity sequencing
A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities
Figure 5-2. Sample Activity-on-Arrow (AOA) Network Diagram for Project X
Arrow Diagramming Method (ADM)
Also called activity-on-arrow (AOA) project network diagrams
Activities are represented by arrows
Nodes or circles are the starting and ending points of activities
Can only show finish-to-start dependencies
Process for Creating AOA Diagrams
1. Find all of the activities that start at node 1.  Draw their finish nodes and draw arrows between node 1 and those finish nodes.  Put the activity letter or name and duration estimate on the associated arrow
2. Continuing drawing the network diagram, working from left to right.  Look for bursts and merges.  Bursts occur when a single node is followed by two or more activities.  A merge occurs when two or more nodes precede a single node
3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies
4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram
Precedence Diagramming Method (PDM)
Activities are represented by boxes
Arrows show relationships between activities
More popular than ADM method and used by project management software
Better at showing different types of dependencies
Figure 5-3. Task Dependency Types
Figure 5-4. Sample Precedence Diagramming Method (PDM) Network Diagram for Project X
Activity Duration Estimating
After defining activities and determining their sequence, the next step in time management is duration estimating
Duration includes the actual amount of time worked on an activity plus elapsed time
People doing the work should help create estimates, and an expert should review them
Schedule Development
Schedule development uses results of the other time management processes to determine the start and end date of the project and its activities
Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project
Important tools and techniques include Gantt charts, PERT analysis, critical path analysis, and critical chain scheduling
Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Symbols include:
A black diamond: milestones or significant events on a project with zero duration
Thick black bars: summary tasks
Lighter horizontal bars: tasks
Arrows: dependencies between tasks
Figure 5-5. Gantt Chart for Project X
Figure 5-6. Gantt Chart for Software Launch Project
Figure 5-7. Sample Tracking Gantt Chart
Critical Path Method (CPM)
CPM is a project network analysis technique used to predict total project duration
A critical path for a project is the series of activities that determines the earliest time by which the project can be completed
The critical path is the longest path through the network diagram and has the least amount of slack or float
Finding the Critical Path
First develop a good project network diagram
Add the durations for all activities on each path through the project network diagram
The longest path is the critical path
Simple Example of Determining the Critical Path
Consider the following project network diagram.  Assume all times are in days.
Figure 5-8.  Determining the Critical Path for Project X
More on the Critical Path
If one of more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken
Misconceptions:
The critical path is not the one with all the critical activities; it only accounts for time
There can be more than one critical path if the lengths of two or more paths are the same
The critical path can change as the project progresses
Using Critical Path Analysis to Make Schedule Trade-offs
Knowing the critical path helps you make schedule trade-offs
Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities
Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date
Table 5-1. Free and Total Float or Slack for Project X
Techniques for Shortening a Project Schedule
Shortening durations of critical tasks for adding more resources or changing their scope
Crashing tasks by obtaining the greatest amount of schedule compression for the least incremental cost
Fast tracking tasks by doing them in parallel or overlapping them
Many Horror Stories Related to Project Schedules
See “What Went Wrong?” example about the National Insurance Recording System
Creating realistic schedules and sticking to them is a key challenge of project management
Importance of Updating Critical Path Data
It is important to update project schedule information
The critical path may change as you enter actual start and finish dates
If you know the project completion date will slip, negotiate with the project sponsor
Critical Chain Scheduling
Technique that addresses the challenge of meeting or beating project finish dates and an application of the Theory of Constraints (TOC)
Developed by Eliyahu Goldratt in his books The Goal and Critical Chain
Critical chain scheduling is a method of scheduling that takes limited resources into account when creating a project schedule and includes buffers to protect the project completion date
Critical chain scheduling assumes resources do not multitask because it often delays task completions and increases total durations
Multitasking Example
Buffers and Critical Chain
A buffer is additional time to complete a task
Murphy’s Law states that if something can go wrong, it will, and Parkinson’s Law states that work expands to fill the time allowed.  In traditional estimates, people often add a buffer and use it if it’s needed or not
Critical chain schedule removes buffers from individual tasks and instead creates
A project buffer, which is additional time added before the project’s due date
Feeding buffers, which are addition time added before tasks on the critical path
Figure 5-10. Example of Critical Chain Scheduling
Program Evaluation and Review Technique (PERT)
PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
PERT uses probabilistic time estimates based on using optimistic, most likely, and pessimistic estimates of activity durations
PERT Formula and Example
PERT weighted average formula:
optimistic time + 4X most likely time + pessimistic time
6
Example:
PERT weighted average =
 8 workdays + 4 X 10 workdays + 24 workdays = 12 days 6
where 8 = optimistic time, 10 = most likely time, and 24 = pessimistic time
Controlling Changes to the Project Schedule
Perform reality checks on schedules
Allow for contingencies
Don’t plan for everyone to work at 100% capacity all the time
Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues
Working with People Issues
Strong leadership helps projects succeed more than good PERT charts
Project managers should use
empowerment
incentives
discipline
negotiation
What Went Right?
Using Software to Assist in Time Management
Software for facilitating communications helps people exchange schedule-related information
Decision support models help analyze trade-offs that can be made
Project management software can help in various time management areas
Table 5-2. Project 98 Features Related to Project Time Management
Words of Caution on Using Project Management Software
Many people misuse project management software because they don’t understand important concepts and have not had good training
You must enter dependencies to have dates adjust automatically and to determine the critical path
You must enter actual schedule information to compare planned and actual progress